World Transport Policy and Practice
  • Menu
  • Articles
    • 1995
    • 1996
    • 1997
    • 1998
    • 1999
    • 2000
    • 2001
    • 2002
    • 2003
    • 2004
    • 2005
    • 2006
    • 2007
    • 2008
    • 2009
    • 2010
    • 2011
    • 2012
    • 2013
    • 2014
    • 2015
    • 2016
    • 2017
    • 2018
    • 2019
    • 2020
    • 2022
    • 2023
    • 2024
    • 2025
    • 2026
    • All
  • For Authors
  • Editorial Board
  • About
  • Issues
  • Blog
  • Donate
  • search
  • RSS feed (opens a modal with a link to feed)

RSS Feed

Enter the URL below into your favorite RSS reader.

http://localhost:44100/feed
ISSN 1352-7614
2026
August 06, 2026 PDT

From Specification to Delivery: Establishing Independent Oversight Mechanisms to Mitigate Rolling Stock Mis-Procurement in U.S. Transit Agencies

Muhammad Ismail, MBA, BSc,
rolling stock procurementtransit policymanufacturing oversightpublic procurement governanceinfrastructure governance
Copyright Logoccby-4.0 • https://doi.org/10.65906/862998llxprf
Photo by Bernd 📷 Dittrich on Unsplash
World Transport Policy and Practice
Ismail, Muhammad. 2026. “From Specification to Delivery: Establishing Independent Oversight Mechanisms to Mitigate Rolling Stock Mis-Procurement in U.S. Transit Agencies.” World Transport Policy and Practice, August 6. https://doi.org/10.65906/862998llxprf.
Save article as...▾

View more stats

Abstract

Rolling stock procurement failures in the United States are rarely the result of a single mistake. More often they develop gradually, accumulating across fragmented institutional practices, poorly drafted specifications, weak vendor assessment, and inadequate factory-level oversight. This article integrates two reform proposals—the Independent Fleet Specification Advisory (IFSA) and the Independent Manufacturing Stage Inspection Advisory (IMSIA)—into a coherent policy framework. Drawing on the Massachusetts Bay Transportation Authority (MBTA)–CRRC Sifang contract as a detailed case study, it traces how procurement breakdowns unfold across the full project lifecycle, from the technical specification phase through to physical delivery. Grounded in principal–agent theory and the literature on public procurement governance, the article argues that creating two independent advisory bodies—one governing pre-contract specification and vendor evaluation, the other governing production-stage quality assurance—is both technically sound and institutionally feasible as a response to systemic mis-procurement risk. The article concludes with policy recommendations for implementation at the federal and agency levels, drawing on compliance gaps documented by federal oversight bodies and the urgency generated by the $66 billion Bipartisan Infrastructure Law rail investment program.

1. Introduction

Rolling stock procurement is among the most consequential capital decisions a transit agency can make. Rail vehicles are long-lived assets, technically demanding, deeply embedded in existing infrastructure, and subject to regulatory requirements that shift over time. Unlike routine commodity purchases, acquiring rail vehicles demands sustained institutional expertise across the whole project—from the first specification drafts and vendor selection through to factory oversight and final delivery. In the United States, that challenge is compounded by a decentralized procurement environment, Buy America rules, and considerable variation in technical standards across jurisdictions (Federal Transit Administration 2023).

The MBTA’s procurement of new Red and Orange Line vehicles from CRRC Sifang—awarded in 2014 at a contract value of roughly $566 million—has become a defining case in this area. What was initially celebrated for its cost savings and domestic manufacturing commitments gradually deteriorated into a prolonged cycle of delivery delays, quality failures, and service disruptions. The costs to passengers, the agency, and the Commonwealth of Massachusetts were substantial (Massachusetts Bay Transportation Authority 2014).

The premise of this article is that the MBTA–CRRC Sifang case is not an anomaly. It is a symptom of structural deficiencies that cut across institutions, processes, and the procurement lifecycle itself. Addressing those calls for institutional innovation, not just better contract language or tighter vendor selection criteria.

The urgency of reform has grown considerably since that contract was signed. The Bipartisan Infrastructure Law (Infrastructure Investment and Jobs Act, Pub. L. 117-58, 2021) directed $66 billion toward rail programs—the largest sustained rail investment since the interstate highway era. Transit agencies that once managed a single major rolling stock procurement per decade are now running two or three simultaneously, against a backdrop of supply chain instability, heightened scrutiny of Chinese OEM relationships under the National Defense Authorization Act for Fiscal Year 2020 (NDAA FY2020, Pub. L. 116-92, § 7613), and increasingly demanding Buy America requirements (National Defense Authorization Act for Fiscal Year 2020 2019). The procurement choices being made right now will determine the reliability of American rail infrastructure for the next generation.

Two complementary reform proposals are advanced here. The first, the Independent Fleet Specification Advisory (IFSA), would be a centralized body providing pre-contract technical guidance, vendor evaluation standards, lifecycle cost modeling, and contract advisory support. The second, the Independent Manufacturing Stage Inspection Advisory (IMSIA), would provide standardized, continuous oversight of the manufacturing process from prototype through serial production to final delivery. Together, they would address the full arc of procurement risk—from what is specified and to whom a contract is awarded, through to whether what is actually built meets the original standard.

The article is organized as follows. Section 2 situates the argument in existing literature, theoretical framing, and documented weaknesses in U.S. transit procurement. Section 3 analyses the MBTA–CRRC Sifang case using publicly available procurement records and federal oversight reports. Sections 4 and 5 develop the IFSA and IMSIA proposals. Section 6 examines the Buy America compliance dimension and the documented gap in independent advisory capacity. Section 7 addresses policy implications and implementation challenges, including governance, funding, and a phased implementation pathway. Section 8 discusses broader limitations. Section 9 concludes.

2. Systemic Weaknesses in U.S. Rolling Stock Procurement

2.1. Theoretical Framework: Principal–Agent Theory and Procurement Governance

The institutional failures documented in U.S. rolling stock procurement come into focus through the lens of principal–agent theory (Jensen and Meckling 1976; Eisenhardt 1989). In this setting, the procuring agency (the principal) contracts with a manufacturer (the agent) whose interests—managing costs, controlling delivery risk, maximizing margin—diverge from the agency’s interest in receiving quality, compliant vehicles on time. Information asymmetry is pervasive: the manufacturer holds detailed knowledge of its production processes, component sourcing, and quality outcomes that the agency cannot independently verify without dedicated oversight (Laffont and Tirole 1993).

Where there are no mechanisms to align incentives and reduce that asymmetry—performance-based contracts, independent manufacturing inspection, verifiable compliance documentation—the agent has both the motive and the means to prioritize its own interests. The IFSA and IMSIA frameworks proposed here are institutional responses to this classic principal–agent problem embedded in complex public procurement (Bajari and Tadelis 2001).

The governance literature reinforces this framing. Uyarra and Flanagan (Uyarra and Flanagan 2010) and Edler and Georghiou (Edler and Georghiou 2007) show that procurement outcomes in technically complex sectors are shaped less by individual contract terms than by the institutional capacity of the procuring organization—its ability to write robust specifications, independently evaluate vendor claims, and monitor contract execution. Comparative studies of transit procurement in the United Kingdom (UK), France, and Japan consistently show that centralized technical advisory functions improve outcomes where they are properly institutionalized (Nash and Smith 2021; Mizutani and Uranishi 2013).

2.2. Institutional Fragmentation

U.S. transit procurement is fundamentally fragmented. Aviation operates under comprehensive federal regulatory authority. Highway infrastructure benefits from standardized federal specifications and design guidance. Transit agencies, by contrast, procure rolling stock with broad autonomy. The Federal Transit Administration (FTA) sets conditions for federal funding—most notably Buy America requirements under 49 U.S.C. § 5323(j) and 49 C.F.R. Part 661—but does not prescribe technical specifications or manufacturing quality standards for rolling stock (U.S. Government Accountability Office 2020).

The result is a proliferation of bespoke procurement processes, each shaped by the preferences and constraints of individual agencies. Specifications diverge. Engineering work is duplicated rather than shared. Lessons learned from one agency’s procurement failures rarely reach others in any systematic way (Lehtonen and Bhave 2017). This fragmentation erodes economies of scale, reduces market transparency, and puts smaller agencies at a particular disadvantage when dealing with sophisticated global manufacturers.

2.3. Capital Cost Bias and Lifecycle Cost Neglect

Infrastructure procurement research consistently identifies a bias toward minimizing upfront capital expenditure at the expense of total lifecycle cost (Flyvbjerg et al. 2003), and rolling stock is no exception. When agencies evaluate bids, initial price tends to dominate, rather than a total cost of ownership (TCO) framework that would account for maintenance expenses, reliability performance, spare parts availability, and end-of-life replacement costs across a vehicle’s thirty- to forty-year operational life.

This bias has several roots. Budget cycles and political timelines create pressure to minimize apparent near-term costs. Federal funding mechanisms may inadvertently amplify this by covering capital expenditure while leaving operations and maintenance to agencies with constrained local budgets. The practical effect is that low bids with elevated lifecycle cost risk are systematically favored over higher bids with stronger long-term value (Iossa and Martimort 2015).

2.4. Vendor Risk in a Globalized Market

The entry of global manufacturers—most notably CRRC, China’s state-owned rail vehicle manufacturer—into U.S. markets has created both competitive opportunity and heightened procurement risk. More competitive bidding can benefit agencies through lower prices and greater supplier choice. But global manufacturers may also present qualitatively different risks from established domestic or European suppliers: limited familiarity with U.S. regulatory frameworks, unfamiliar quality management systems, supply chains spanning multiple jurisdictions, and exposure to geopolitical and trade policy uncertainty (Congressional Research Service 2020).

The NDAA FY2020 imposed progressive restrictions on the use of CRRC-manufactured rolling stock in federally funded transit systems. New procurements are being directed toward alternative OEMs—many of whom are unfamiliar to U.S. agencies and untested in the U.S. regulatory environment. That transition creates a fresh demand for independent advisory expertise with direct knowledge of Asian OEM manufacturing settings.

2.5. Manufacturing Oversight Deficiencies

Beyond specification and vendor selection, a critical and underappreciated vulnerability in U.S. transit procurement is the inadequacy of manufacturing-stage oversight. Once contracts are awarded, agencies typically rely on small project-specific inspection teams, third-party consultants with limited authority, or vendor self-certification for critical subsystems (American Public Transportation Association 2019). This is poorly suited to modern rolling stock manufacturing, which involves distributed component production across multi-tier global supply chains, final assembly in domestic facilities, and the integration of complex mechanical, electrical, and software systems.

The result is a reactive quality model: defects are frequently discovered after vehicles have entered revenue service, at which point remediation is expensive, disruptive, and legally contentious. A more proactive approach—one that embeds independent inspection authority throughout the manufacturing lifecycle—would identify and resolve deficiencies before they propagate across production runs and before defective vehicles reach passengers.

2.6. The Documented Federal Compliance Gap

These structural weaknesses are not simply concerns raised by outside observers. They are findings that the federal government’s own oversight bodies have returned, repeatedly, across successive audit cycles.

The Department of Transportation’s Office of Inspector General (DOT OIG) has issued multiple reports finding that transit agencies routinely lack the internal technical capacity to verify OEM Buy America documentation against actual manufacturing practice. Pre-award audits are often inadequate; domestic content claims are accepted on the basis of manufacturer self-certification rather than independent verification; and compliance disputes discovered after delivery have delayed service entry, triggered federal investigations, and in some cases put agencies at risk of losing future federal funding (U.S. Department of Transportation, Office of Inspector General 2024; 2019).

The Government Accountability Office (GAO) has reached parallel conclusions. In reviews of major transit capital programs, the GAO observed that agencies routinely award contracts without performance-based specifications robust enough to protect their interests against international OEMs, and recommended that the FTA develop clearer guidance on specification writing for international competitive tenders (U.S. Government Accountability Office 2019; 2010).

These are not one-off observations. They are the recurring conclusions of oversight bodies conducting successive audit cycles—precisely because the underlying problem has not been resolved. The gap is real, it is documented, and it carries substantial costs.

3. Case Study: The MBTA–CRRC Sifang Procurement

3.1. Data Sources and Methodological Note

The analysis in this section draws on publicly available primary sources: FTA grant documentation, the Commonwealth of Massachusetts Office of the Inspector General review of MBTA rolling stock procurement practices (Commonwealth of Massachusetts, Office of the Inspector General 2023a), MBTA Board of Directors minutes and public records, DOT OIG audit reports (U.S. Department of Transportation, Office of Inspector General 2024; 2019), and Congressional Research Service analysis of CRRC’s market entry (Congressional Research Service 2020). Supplementary context comes from published investigative reporting (Saltzman and Finucane 2022) and Transportation Research Board guidance (Transportation Research Board 2016). Some operational data—including the full scope of acceptance testing failures and contractual remediation correspondence—remains confidential under the MBTA–CRRC Sifang agreement and cannot be independently verified in the public record.

3.2. Project Overview and Context

In 2014, the MBTA awarded CRRC Sifang America a contract worth approximately $566 million for the design, manufacture, and delivery of new vehicles for the Red and Orange Lines (Massachusetts Bay Transportation Authority 2014). Several features made it notable. CRRC was then a relatively new entrant to the U.S. market but offered a substantially lower bid than competitors. The contract required the establishment of an assembly facility in Springfield, Massachusetts, satisfying Buy America domestic content requirements. Cost savings and local job creation made it politically attractive.

Those early advantages did not last. Over the course of the project, the MBTA experienced significant delivery delays. Quality concerns emerged during and after acceptance testing, including recurring door system malfunctions, electrical and battery faults, and derailment incidents linked to manufacturing tolerances and assembly quality. Integration challenges arose with existing MBTA infrastructure. Collectively, these problems imposed maintenance burdens, reduced service reliability, and damaged public confidence in both the agency and the procurement outcome (Saltzman and Finucane 2022; Commonwealth of Massachusetts, Office of the Inspector General 2023a).

3.3. Operational Impact: Secondary Evidence

The downstream operational consequences of the MBTA–CRRC Sifang procurement failures are documented across multiple public records and investigative sources. Taken together, they illustrate the scale of systemic mis-procurement costs.

Service disruptions were recurrent and prolonged. Following the detection of door system malfunctions and battery faults on the new Orange Line cars, the MBTA was forced to remove vehicles from service on multiple occasions between 2019 and 2023, triggering cascading delays and overcrowding on one of Boston’s most-used transit corridors. In August 2022, following a serious derailment incident involving an Orange Line train near Sullivan Square, the entire Orange Line was taken out of service for a full month for emergency inspections and repairs—the first complete line shutdown in the MBTA’s modern history (Saltzman and Finucane 2022). While multiple factors contributed to that shutdown, the vehicle quality issues attributable to the CRRC procurement were a material contributor.

Vehicle withdrawals were systematic. The MBTA’s own board records document repeated removal of newly delivered CRRC vehicles from revenue service pending resolution of defects identified in acceptance testing. As of late 2022, a significant portion of the Orange Line fleet remained under corrective action programs, requiring the agency to retain older, less reliable vehicles in service beyond their planned retirement dates, compounding maintenance costs and service unreliability.

Reputational damage to the MBTA was substantial and measurable. Rider satisfaction surveys conducted by the Massachusetts Department of Transportation recorded declining confidence in service reliability across the Orange and Red Lines during the period of peak vehicle quality failures. Legislative scrutiny intensified, with the Massachusetts legislature convening hearings on MBTA capital program management and procurement governance. Media coverage of the CRRC procurement failures was extensive and sustained (Saltzman and Finucane 2022), contributing to a broader reputational crisis for the agency that accelerated leadership changes and prompted a comprehensive federal safety inspection in 2022.

Customer complaints and service performance metrics reinforced this picture. On-time performance on the Orange Line declined sharply during periods when fleet availability was reduced by vehicle withdrawals, falling below 60% in some reporting periods against a system benchmark of 80%. These downstream costs—service disruption, vehicle withdrawals, reputational damage, customer dissatisfaction, regulatory intervention, and leadership turnover—represent a systemic cost that far exceeded any savings achieved through the lower initial contract price (Commonwealth of Massachusetts, Office of the Inspector General 2023a).

3.4. Specification and Vendor Selection Failures

Analysis of the MBTA procurement suggests that foundational decisions at the specification and vendor evaluation stages contributed substantially to the difficulties that followed.

The evaluation of CRRC’s bid was heavily weighted toward initial contract price, without adequate adjustment for execution risk factors specific to the vendor’s limited U.S. experience. CRRC had not previously delivered rolling stock to U.S. transit agencies operating under FTA regulatory frameworks, and this unfamiliarity introduced risks that were neither properly priced nor contractually mitigated at the award stage (Procurement Executive Advisory Council 2021).

Technical specifications incorporated a degree of customization that increased design complexity and integration risk. Standardized specifications—benchmarked against proven designs and consistent across multiple procurements—would likely have reduced that complexity, improved vendor understanding of requirements, and eased integration with existing MBTA infrastructure.

Contractual provisions for performance guarantees, milestone-based payments, and penalty mechanisms were also insufficiently robust to incentivize timely, quality-compliant delivery. When delays and defects materialized, the agency’s ability to enforce remediation was constrained by what had been originally agreed. The direct causal link between these specification-phase weaknesses and the procurement outcomes described in Section 3.3 is clear: inadequate vendor risk assessment allowed execution risk to be underpriced at award; bespoke specifications amplified integration failure probability; and weak penalty mechanisms reduced the manufacturer’s incentive to prioritize quality. These are precisely the deficiencies that the IFSA framework proposed in Section 4 is designed to address.

3.5. Manufacturing-Stage Failures

The production phase exposed further weaknesses. The manufacturing structure involved carbody and major component production at overseas facilities, with final assembly at the Springfield plant. That distributed model placed considerable demands on quality assurance oversight across multiple jurisdictions and supply chain tiers—demands the MBTA’s inspection regime was not equipped to meet.

Evidence from publicly available OIG and Commonwealth Inspector General reports indicates that inspection coverage at overseas supplier facilities was limited, that inspectors’ authority to halt production upon defect detection was constrained, and that quality assurance operated reactively rather than preventively (Commonwealth of Massachusetts, Office of the Inspector General 2023a). Door system reliability issues, which ultimately required remedial campaigns across the fleet, might well have been detectable—and correctable—at the prototype and first-article stages under rigorous independent inspection. Instead, flawed designs were scaled into serial production, with defects propagating across multiple vehicle units before systematic remediation was undertaken. This manufacturing-phase failure pattern maps directly onto the absence of the stage-gate inspection framework that the IMSIA (Section 5.2) would provide: had mandatory checkpoints been in place at prototype and first-article stages, the door system defects would have triggered formal corrective action before mass production began.

3.6. The Buy America Dimension

The distributed manufacturing structure—carbody components produced overseas, final assembly in Springfield—required careful documentation of domestic content percentages across every major subsystem. Verifying those percentages demanded physical inspection at production facilities against build records. The DOT OIG’s 2024 audit of the Southeastern Pennsylvania Transportation Authority’s (SEPTA’s) Buy America compliance identified precisely this verification deficit as a systemic problem across FTA-funded procurements (U.S. Department of Transportation, Office of Inspector General 2024)—a finding consistent with the structural gap visible in the MBTA case.

3.7. Accountability and Lessons

The absence of clear inspection records and defined accountability frameworks complicated efforts to assign contractual responsibility and pursue remediation through legal channels. The total cost of the procurement failures—measured across service disruption costs, vehicle remediation programs, extended operation of older fleet, legal costs, and reputational damage—far exceeded any savings achieved through the lower initial contract price (Commonwealth of Massachusetts, Office of the Inspector General 2023a).

This experience encapsulates the central argument of this article: rolling stock procurement failures are systemic rather than episodic, and they require institutional responses capable of addressing risk across the full procurement lifecycle.

4. The Independent Fleet Specification Advisory (IFSA)

4.1. Concept and Institutional Role

The IFSA would function as a centralized expert body providing technical guidance, evaluation standards, and data-driven support to transit agencies throughout the pre-contract phase of rolling stock procurement. Critically, it would not replace agency decision-making authority—transit agencies would retain responsibility for their procurement choices. Rather, the IFSA would strengthen the institutional capacity available to agencies, particularly smaller ones with limited internal technical staff, by providing resources, benchmarks, and advisory expertise that no individual agency could reasonably sustain on its own (Transportation Research Board 2016).

The IFSA model draws on analogues elsewhere. Aviation benefits from the FAA’s technical standards and type certification processes, which impose rigorous design and performance requirements on manufacturers regardless of which airline is purchasing a given aircraft. The EU Agency for Railways (ERA) coordinates technical specifications for interoperability across member states (European Union Agency for Railways 2022). The UK’s Rail Safety and Standards Board provides centralized technical research and standards development for the British rail industry. U.S. rolling stock procurement lacks a comparable institutional architecture, and the IFSA is conceived as a partial remedy.

4.2. Core Functions

4.2.1. Specification Standardization

Perhaps the most consequential contribution an IFSA could make is the development and maintenance of baseline technical specifications for different categories of rolling stock—heavy rail, light rail, commuter rail, and bus rapid transit. These baselines would not eliminate all customization, which may be genuinely necessary given the diversity of U.S. transit systems, but would establish a floor of standardized requirements, reducing unnecessary divergence and the associated costs of bespoke engineering (European Union Agency for Railways 2022).

Standardized specifications would also improve interoperability across agencies, where shared standards enable component compatibility and cooperative maintenance, and across time, where consistent specifications reduce the complexity of mid-life modifications and replacements. The IFSA would craft specifications robust enough to protect agency interests against sophisticated global manufacturers—specifying not just what they need a vehicle to do, but how maintainability, reliability, and total cost of ownership will be measured and enforced.

4.2.2. Independent Vendor Evaluation

The IFSA would conduct or accredit independent assessments of manufacturers competing for U.S. transit contracts. These would cover technical capability, past performance, financial stability, supply chain maturity, and regulatory compatibility with FTA frameworks (International Organisation for Standardisation 2015). Risk-adjusted scoring frameworks would allow procurement panels to weigh low bids against execution risk, ensuring that cost competitiveness is assessed alongside capability and reliability.

Had such a framework been applied to the MBTA–CRRC Sifang procurement, CRRC’s limited prior experience with FTA regulatory requirements and U.S. operational environments would have been systematically factored in—potentially yielding a different assessment of the bid or stronger contractual risk mitigation requirements.

4.2.3. Total Cost of Ownership Modeling

The IFSA would develop and disseminate standardized total cost of ownership (TCO) frameworks, enabling agencies to evaluate bids on projected lifecycle cost rather than capital price alone. TCO modeling would incorporate maintenance cost projections, reliability benchmarks, spare parts availability, training costs, and end-of-life considerations across a vehicle’s operational life (Flyvbjerg et al. 2003).

This shift from capital cost to lifecycle cost as the primary evaluation metric would structurally reduce the incentive to accept low bids carrying elevated long-term financial risk—a chronic vulnerability in current U.S. transit procurement, directly traceable in the MBTA case to the capital cost bias described in Section 2.3.

4.2.4. Knowledge Repository and Performance Data

The IFSA would maintain a centralized repository of procurement outcomes, fleet performance metrics, failure reports, and lessons learned from completed procurements across U.S. transit agencies. This would serve as an institutional memory, correcting the current situation in which procurement failures are repeated because agencies lack access to structured, comparable data from their peers’ experiences (Lehtonen and Bhave 2017).

Access to global performance data—including outcomes from comparable procurements in other national transit systems and patterns of manufacturing defects across OEM facilities—would provide early-warning signals on manufacturer reliability, emerging technical risks, and best practices in contract design. Production quality data gathered through IMSIA oversight would feed directly into this repository.

4.2.5. Contract Advisory Services and Buy America Guidance

The IFSA would develop model contract structures incorporating performance-based milestone payments, enforceable penalty mechanisms, risk-sharing provisions, and inspection rights that agencies could adapt to their circumstances. Advisory support from IFSA specialists during contract negotiation would strengthen agencies’ positions relative to sophisticated global manufacturers.

Critically, the IFSA would also provide specialized guidance on Buy America compliance—including pre-award audit protocols, domestic content verification methodologies, and documentation standards that move beyond manufacturer self-certification toward independently verifiable evidence of compliance. This directly addresses the recurring deficiency documented by the DOT OIG across multiple audit cycles (U.S. Department of Transportation, Office of Inspector General 2024; 2019).

5. The Independent Manufacturing Stage Inspection Advisory (IMSIA)

5.1. Concept and Institutional Role

Where the IFSA addresses the pre-contract phase, the IMSIA addresses the production phase—the period between contract award and vehicle delivery during which design intent must be translated into physical assets. The IMSIA is conceived as a centralized, independent body deploying expert inspection teams across manufacturing sites to provide continuous, standardized oversight of rolling stock production (American Public Transportation Association 2019).

The IMSIA differs fundamentally from the project-specific inspection consultants agencies typically engage. Unlike consultants operating under agency direction and within narrow contractual mandates, the IMSIA would operate independently of both the procuring agency and the manufacturer. It would hold institutional authority—backed by contractual provisions and regulatory recognition—to mandate corrective action and, in cases of major defect, to halt production pending remediation. Its continuity across projects and agencies would build inspection expertise that no individual agency procurement can sustain.

5.2. Stage-Gate Inspection Framework

The IMSIA’s central operational mechanism would be a stage-gate inspection framework: a sequence of mandatory checkpoints at defined manufacturing milestones, at each of which independent inspectors would formally assess compliance before authorizing production to proceed (International Railway Industry Standard 2020). Proposed stage gates would include:

  • Design finalization review, confirming specifications are complete, unambiguous, and consistent with contracted requirements

  • Prototype manufacturing inspection, subjecting the first vehicle to comprehensive assessment against design and performance standards

  • First article inspection, evaluating the first serially produced unit to confirm that manufacturing processes yield results consistent with prototype performance

  • Serial production audits, using statistical sampling to verify ongoing quality compliance

  • Pre-shipment validation, inspecting vehicles against a final acceptance standard before release from the manufacturing facility

The stage-gate model prevents defects from propagating across production runs. As demonstrated in the MBTA case (Section 3.5), the door system reliability failures that ultimately required remedial campaigns across the entire fleet were identified only after defective designs had been scaled into serial production. Under the IMSIA stage-gate framework, a door system reliability issue identified at the prototype inspection stage would trigger formal corrective action and a mandatory design modification before mass production was authorized. The financial and operational savings from such early intervention—measured against the costs of fleet-wide remediation, service disruptions, and passenger impact documented in Section 3.3—would far exceed the cost of the inspection framework itself.

5.3. Embedded Inspection Teams and Supplier Chain Oversight

The IMSIA would deploy multidisciplinary inspection teams—comprising mechanical engineers, electrical systems specialists, and quality assurance professionals—physically present at both final assembly facilities and critical component manufacturing sites. Oversight would extend beyond the prime contractor to Tier-1 and Tier-2 suppliers of critical components. Without visibility into upstream manufacturing, final assembly inspection can only catch defects after they have already been built into vehicles (Commonwealth of Massachusetts, Office of the Inspector General 2023b).

5.4. The Asian OEM Context

NDAA FY2020 restrictions on CRRC-manufactured rolling stock have redirected new U.S. procurements toward alternative OEMs, many of whom are unfamiliar to U.S. agencies and untested in the U.S. regulatory environment. This creates renewed demand for inspection expertise with direct knowledge of Asian OEM manufacturing environments—the capacity to assess whether a manufacturer’s documentation practices and quality control processes are reliable, independently of the manufacturer’s own representations. This is a form of tacit, practice-based knowledge in Polanyi’s (Polanyi 1966) sense: knowledge embodied in practitioner experience rather than codifiable in regulatory text.

The IMSIA would institutionalize this expertise as an organizational asset rather than leaving it dependent on individual consultant relationships, ensuring its availability across the full range of FTA-funded procurements affected by NDAA transition requirements.

5.5. Digital Monitoring and Real-Time Reporting

The IMSIA would establish digital systems for production quality monitoring, enabling real-time tracking of defect rates, inspection outcomes, and corrective action status across all active manufacturing sites. Remote auditing capabilities would supplement embedded inspection, enabling rapid assessment of production data without requiring inspectors to travel to every site for every audit cycle (National Institute of Standards and Technology 2022). This data infrastructure would also feed the IFSA knowledge repository, enriching the evidence base available to agencies undertaking future procurements.

5.6. Intervention Authority

The IMSIA’s effectiveness depends critically on its authority to act when defects are identified. It would need formally recognized stop-work authority for major defects, mandated corrective action protocols with defined timelines, and escalation mechanisms to funding authorities and agency leadership when manufacturers fail to comply with inspection directives.

This authority would require contractual recognition—IMSIA inspection rights and intervention powers would need to be embedded in procurement contracts from the outset—as well as alignment with federal procurement regulations governing FTA-funded projects. Implementation would be a condition of federal capital funding, incentivizing agency adoption.

5.7. Summary: IFSA and IMSIA Roles, Functions, and Outputs

Table 3 below provides a comparative summary of the two proposed bodies, clarifying their distinct roles, operational scope, and institutional authority within the procurement lifecycle.

Table 3.Comparative Summary of IFSA and IMSIA Roles and Functions
Dimension IFSA IMSIA
Procurement Phase Pre-contract (specification through award) Post-award (prototype through delivery)
Primary Role Advisory – technical guidance, standards, evaluation Oversight – independent inspection, quality assurance
Authority Level Advisory (non-binding recommendations to agencies) Regulatory-adjacent (stop-work, corrective action mandate)
Key Outputs Baseline specifications, TCO models, vendor evaluation reports, Buy America audit guidance Stage-gate inspection reports, corrective action directives, production quality data
Knowledge Contribution Pre-procurement risk intelligence, procurement outcome repository Manufacturing quality data feed to IFSA repository
Institutional Analogue EU Agency for Railways (ERA); UK Rail Safety and Standards Board International Railway Industry Standard (IRIS) certification body; aviation type certification oversight

6. The Buy America Compliance Gap and the Case for Independent Advisory

6.1. Why Existing Practitioners Cannot Fully Fill the Gap

A transit agency preparing for a major rolling stock procurement funded by a Capital Investment Grant under 49 U.S.C. § 5309 needs three capabilities that are almost never found within a single independent authority: the ability to write performance-based technical specifications; the ability to physically verify at manufacturing facilities that what is being built matches what was contracted; and the ability to review Buy America documentation with enough manufacturing knowledge to identify discrepancies between claimed and actual domestic content.

In theory, an agency could hire three separate specialists for these functions. In practice, the handoffs between them create precisely the gaps where problems hide. The gap is structural, not accidental, and is documented in the federal oversight record (U.S. Department of Transportation, Office of Inspector General 2024; 2019).

Table 1.Practitioner Capability Matrix and Structural Gap
Practitioner Type Strengths Critical Limitations
Transportation attorneys Deep knowledge of Buy America law, FTA regulations, waiver procedures Lack factory-floor credibility; cannot independently verify whether OEM documentation reflects physical reality
Domestic rail engineers Technical knowledge of U.S. standards and operations Rarely have direct experience at Asian OEM facilities; limited exposure to international procurement legal risk
OEM in-house compliance teams Detailed manufacturing knowledge Represent the manufacturer's interests, not the agency's; structural conflict of interest in Buy America self-certification
IFSA/IMSIA independent advisory (proposed) Combines specification writing, OEM facility inspection, and Buy America advisory from the agency's side New institutional model requiring establishment; effectiveness depends on sustained funding and governance quality

6.2. Federal Documentation of the Gap

The federal government’s own oversight bodies have documented this gap in published reports across multiple audit cycles. The DOT OIG’s 2024 audit of SEPTA’s Buy America compliance found that FTA’s oversight mechanisms faced significant challenges in verifying domestic content claims against actual manufacturing practice (U.S. Department of Transportation, Office of Inspector General 2024). The same office’s 2019 report found that transit agencies routinely lacked the internal technical capacity to conduct meaningful pre-award audits, relying instead on manufacturer self-certification (U.S. Department of Transportation, Office of Inspector General 2019). GAO reviews of transit capital programs recommended that FTA develop clearer guidance on specification writing for international competitive tenders (U.S. Government Accountability Office 2019; 2010).

Table 2.Key Federal Documents Establishing the Compliance Gap
Document Source Significance
DOT OIG Rep. No. ZA2024033 (July 31, 2024) U.S. Dept. of Transportation OIG Federal documentation of Buy America compliance failures in FTA-funded procurements
DOT OIG Rep. No. ZA2019048 (Apr. 3, 2019) U.S. Dept. of Transportation OIG Recurring inadequacy findings in rolling stock specification and oversight
GAO-19-562; GAO-10-730 U.S. Government Accountability Office Documented agency incapacity for performance-based specification writing
FTA Buy America regulations, 49 C.F.R. Part 661 Federal Transit Administration Regulatory complexity establishing demand for specialized advisory
IIJA, Pub. L. 117-58 (2021) U.S. Congress Quantifies the $66 billion investment surge and concurrent procurement volume
NDAA FY2020, Pub. L. 116-92, § 7613 National Defense Authorization Act Establishes U.S.-specific need for Asian OEM expertise in procurement advisory

6.3. The IIJA Investment Window

The $66 billion directed by the Bipartisan Infrastructure Law will not remain available indefinitely. The procurement decisions being made now will shape U.S. rail infrastructure for a generation. The value of independent advisory institutions is greatest during the window in which those decisions are being made—a window that is already open and will eventually close.

Getting the specifications wrong, or failing to catch a Buy America documentation problem before contract award, is not a correctable error. It is a thirty-year mistake.

7. Policy Implications and Implementation Considerations

7.1. Preferred Governance Model

While Section 7.2 discusses the full range of institutional options, the analysis points toward a preferred governance architecture: a hybrid model in which the FTA establishes minimum performance standards and accredits IFSA and IMSIA functions, while delivery is carried out through a multi-agency consortium governed by participating transit authorities. This structure offers three key advantages.

First, it preserves agency autonomy—transit authorities retain procurement decision-making responsibility and share governance of the advisory bodies. Second, it benefits from federal authority and funding leverage: the FTA’s accreditation role ensures minimum standards are applied consistently across all federally funded procurements. Third, it distributes operating costs equitably across beneficiary agencies rather than concentrating them in the federal budget.

Independence safeguards are central to this model’s credibility. The IFSA and IMSIA governing boards should be constituted to ensure structural independence: a majority of seats held by transit agency representatives not currently engaged in active procurements under review, with mandatory recusal provisions for conflicts of interest; independent technical experts appointed through an open, merit-based process; and no seats held by manufacturers or their legal representatives. All inspection reports, vendor evaluation outcomes, and audit findings would be published to the IFSA knowledge repository, subject only to narrow commercial confidentiality protections.

Accountability mechanisms would include an independent performance audit of each body every three years, conducted by a review panel including DOT OIG representation, with results reported to Congress and published. Both bodies would be subject to annual performance metrics, including procurement outcome tracking from agencies they advise and inspection accuracy rates measured against post-delivery defect records.

7.2. Institutional Architecture Options

The IFSA and IMSIA could alternatively be established as fully independent bodies under the FTA, or as purely voluntary multi-agency consortia without federal accreditation. The FTA-only model would offer the broadest authority and most consistent standards application, but would require federal appropriations and may face political resistance from agencies protective of procurement autonomy. The voluntary consortium model might prove more flexible but risks inconsistent adoption and inadequate funding stability.

The preferred hybrid arrangement—described above—balances these considerations. Comparable arrangements exist in other federal infrastructure domains: the Federal Highway Administration sets standards and conditions for funding while state departments of transportation implement programs. The FTA already plays an analogous role in capital program oversight; extending this to include IFSA and IMSIA accreditation is an incremental rather than structural change.

7.3. Funding Mechanisms

Operating costs for both bodies should be funded through a combination of federal appropriations and agency procurement levies. A per-contract contribution structure—calibrated to procurement value, with sliding-scale rates that do not disadvantage smaller agencies—would ensure that the agencies generating demand for advisory services contribute to the cost of supplying them. Federal seed funding during the establishment and capacity-building phase (estimated at three to five years) would be justified by the documented cost of mis-procurement and the scale of the Infrastructure Investment and Jobs Act (IIJA) investment at risk.

International precedents support this approach. The EU Agency for Railways is funded through a combination of European Union budget contributions and fees charged to railway undertakings and infrastructure managers for certification services (European Union Agency for Railways 2022). The International Railway Industry Standard (IRIS) certification program is sustained through industry membership fees and certification charges (International Railway Industry Standard 2020). Adapted versions of these cost-recovery mechanisms could function within the U.S. federal grant framework.

Given the substantial costs that mis-procurement imposes—through remediation, service disruptions, reputational damage, and regulatory intervention—the investment in independent advisory capacity is readily justifiable on cost-benefit grounds. The MBTA case alone illustrates costs running into hundreds of millions of dollars in excess of the original contract value (Commonwealth of Massachusetts, Office of the Inspector General 2023a).

7.4. Phased Implementation Pathway

A realistic implementation strategy would proceed in three phases, recognizing that the institutional capacity required cannot be assembled immediately.

Phase 1 (Years 1–2): Establishment and Piloting. The FTA would publish an enabling rule establishing IFSA and IMSIA as accredited functions under the Capital Investment Grant program. A consortium of five to eight large transit agencies—including those with active procurements under the IIJA program—would form the founding governance consortium. IFSA functions (specification standardization, TCO modeling, vendor evaluation) would be piloted on two to three active procurements, with IMSIA oversight piloted on one overseas manufacturing program. FTA would provide seed funding and establish a cross-agency working group to develop standard inspection protocols.

Phase 2 (Years 3–5): Scaling and Mandatory Adoption. Participation in IFSA advisory services would become a condition of FTA Capital Investment Grant eligibility for new rolling stock procurements. IMSIA oversight would be required for procurements above a defined contract value threshold (initially, contracts exceeding $100 million). The knowledge repository would be populated from pilot program outcomes and opened to all participating agencies. The first triennial performance audit would be conducted.

Phase 3 (Year 5 onwards): Full Operation. All FTA-funded rolling stock procurements would operate within the IFSA/IMSIA framework. Cost-sharing levies would replace federal seed funding as the primary operating cost source. The bodies would develop into regional substructures to manage workload as the IIJA procurement pipeline reaches full volume.

Participation would initially be incentive-based—agencies choosing to participate in the pilot phase would receive priority processing for capital grant applications. Mandatory participation, as a condition of federal funding, would follow once the framework is demonstrated to function and its value to agencies is established.

7.5. Legislative and Regulatory Enablers

Full implementation would require enabling action at both the regulatory and legislative levels. At the regulatory level, FTA rulemaking could establish IFSA and IMSIA accreditation as Capital Investment Grant conditions under existing statutory authority. At the legislative level, a modest appropriation—potentially structured as a set-aside within the IIJA rail program—would fund the establishment phase. Congressional authorization for the multi-agency consortium governance structure would provide the legal foundation for participating agencies to share procurement data and coordinate funding contributions.

7.6. Balancing Standardization and Agency Autonomy

A legitimate concern about centralized advisory bodies is potential encroachment on agency autonomy. The IFSA and IMSIA as proposed are advisory and oversight bodies, not directive authorities. Agencies would retain decision-making authority over their procurement choices while benefiting from enhanced technical capacity and standardized frameworks. IFSA baseline specifications would establish floors rather than ceilings; agencies with specific operational requirements could adopt enhanced or modified standards.

7.7. Addressing Industry Resistance

Manufacturers may resist enhanced oversight, particularly the IMSIA’s stop-work authority and supplier chain audit rights. Engaging manufacturers during the design phase of the advisory bodies—establishing transparent, consistently applied inspection protocols and providing manufacturers with clear procedural rights in the corrective action process—would reduce adversarial dynamics and build confidence in the framework (International Railway Industry Standard 2020).

It is also worth noting that reputable manufacturers with robust quality systems have relatively little to fear from rigorous independent inspection. A well-designed IMSIA would function as a quality signal, rewarding manufacturers whose systems consistently meet standards and creating competitive disadvantage for those that do not.

8. Challenges and Limitations

The proposals advanced here face real implementation challenges that deserve honest acknowledgment.

Jurisdictional complexity is inherent to any body operating across the geographic and regulatory diversity of U.S. transit procurement. IMSIA inspection at overseas manufacturing sites raises questions of legal authority, access rights, and enforcement jurisdiction that will require careful contractual and potentially treaty-level design. Political resistance from agencies protective of procurement autonomy, and from manufacturers concerned about oversight burden, will need sustained engagement and careful institutional design to navigate.

Resource intensity is a genuine constraint. Maintaining expert inspection teams capable of evaluating complex rolling stock manufacturing—across mechanical, electrical, and software subsystems—requires a sustained investment in specialist human capital that cannot be assembled quickly. A transitional period of capacity building, drawing on existing expertise within agencies, federal bodies, and the private sector, would be necessary.

Data sharing presents technical and governance challenges. Agencies may be reluctant to share procurement outcome data over concerns about revealing operational vulnerabilities or commercially sensitive information. Manufacturers may resist disclosure of production quality metrics on proprietary grounds. Governance frameworks for the IFSA knowledge repository would need robust data protection provisions and clearly defined access rules.

The pace of rolling stock technology change—battery-electric and hydrogen propulsion, advanced digital control systems, connectivity infrastructure—means that both IFSA specification frameworks and IMSIA inspection protocols would require continuous updating. Institutional agility must be designed in from the outset.

Finally, this article’s case study analysis is based primarily on publicly available documentary evidence and secondary sources, given the confidentiality constraints that apply to active procurement and litigation matters. Future research should seek primary data through interviews with procurement officials, Freedom of Information Act (FOIA)-obtained inspection records, and comparative case studies involving other U.S. transit agencies. The generalizability of findings from a single—if highly documented—case to the broader population of U.S. transit procurements should be assessed through such comparative work.

9. Conclusion

The MBTA–CRRC Sifang procurement illustrates, with clarity, the consequences of systemic weaknesses in U.S. rolling stock procurement practice. Fragmented institutional capacity, capital cost bias, inadequate vendor risk assessment, Buy America documentation gaps, and manufacturing oversight deficiencies collectively produced an outcome that fell far short of its initial promise—at significant cost to the agency, to federal funders, and to the passengers who depend on reliable public transit.

This article has argued that addressing these weaknesses requires institutional innovation across the full procurement lifecycle, grounded in principal–agent theory and the comparative literature on public procurement governance. The Independent Fleet Specification Advisory would strengthen the pre-contract phase by standardizing specifications, improving vendor evaluation, institutionalizing lifecycle cost analysis, building procurement knowledge, and advising on contract design and Buy America compliance. The Independent Manufacturing Stage Inspection Advisory would address the production phase by embedding continuous, standardized, and authoritative inspection from prototype through serial production to delivery.

Together, these bodies represent a structurally coherent response to a structurally embedded problem. They shift U.S. transit procurement from a reactive model—discovering defects and compliance failures after vehicles enter service—to a proactive one that builds quality and accountability into rolling stock from specification through delivery. The proposed hybrid governance model, combining FTA accreditation with multi-agency consortium delivery, provides a practical institutional pathway that balances federal authority with agency autonomy.

The implementation challenges are real but surmountable, and a phased approach—piloting IFSA and IMSIA functions on active procurements before scaling to mandatory adoption—reduces implementation risk while building the institutional capacity and evidence base needed for durable reform. The cost of inaction—measured in procurement failures, service disruptions, compliance disputes, and eroded public confidence—is demonstrably high.

The Bipartisan Infrastructure Law has created a window of urgency: $66 billion is flowing into rolling stock procurement programs across dozens of agencies simultaneously, and the decisions made during this period will shape American rail infrastructure for a generation. The lessons of the MBTA case are not confined to Massachusetts. They speak to every transit agency that procures rolling stock under conditions of limited institutional capacity, decentralized governance, Buy America complexity, and intensifying global market competition. Institutional reform of the kind proposed here would benefit not only individual agencies but the U.S. public transit system as a whole—and ultimately the passengers it exists to serve.

References

American Public Transportation Association. 2019. Rail Transit Vehicle Inspection Standards and Practices. APTA Standards Development Program.
Bajari, P., and S. Tadelis. 2001. “Incentives versus Transaction Costs: A Theory of Procurement Contracts.” RAND Journal of Economics 32 (3): 387–407. https:/​/​doi.org/​10.2307/​2696361.
Google Scholar
Commonwealth of Massachusetts, Office of the Inspector General. 2023a. Review of MBTA Rolling Stock Procurement Practices. Executive Office of Administration and Finance. https:/​/​www.mass.gov/​orgs/​office-of-the-inspector-general.
Commonwealth of Massachusetts, Office of the Inspector General. 2023b. Review of MBTA Rolling Stock Procurement Practices. Executive Office of Administration and Finance.
Congressional Research Service. 2020. CRRC and U.S. Transit Procurement: National Security Considerations. No. R46337. Library of Congress.
Edler, J., and L. Georghiou. 2007. “Public Procurement and Innovation—Resurrecting the Demand Side.” Research Policy 36 (7): 949–63. https:/​/​doi.org/​10.1016/​j.respol.2007.03.003.
Google Scholar
Eisenhardt, K. M. 1989. “Agency Theory: An Assessment and Review.” Academy of Management Review 14 (1): 57–74. https:/​/​doi.org/​10.2307/​258191.
Google Scholar
European Union Agency for Railways. 2022. Technical Specifications for Interoperability: Rolling Stock Subsystems. ERA/TD/2022. https:/​/​www.era.europa.eu.
Federal Transit Administration. 2023. “Buy America Requirements for Rolling Stock Procurement.” U.S. Department of Transportation. https:/​/​www.transit.dot.gov/​regulations-and-guidance/​buy-america.
Flyvbjerg, B., M. S. Holm, and S. Buhl. 2003. “How Common and How Large Are Cost Overruns in Transport Infrastructure Projects?” Transport Reviews 23 (1): 71–88. https:/​/​doi.org/​10.1080/​01441640309904.
Google Scholar
International Organisation for Standardisation. 2015. ISO 9001:2015 Quality Management Systems—Requirements. ISO.
Google Scholar
International Railway Industry Standard. 2020. IRIS Revision 03: Quality Management System Requirements for Railway Industry Organizations. UNIFE. https:/​/​www.iris-certification.org.
Iossa, E., and D. Martimort. 2015. “The Simple Microeconomics of Public–Private Partnerships.” Journal of Public Economic Theory 17 (1): 4–48. https:/​/​doi.org/​10.1111/​jpet.12114.
Google Scholar
Jensen, M. C., and W. H. Meckling. 1976. “Theory of the Firm: Managerial Behavior, Agency Costs and Ownership Structure.” Journal of Financial Economics 3 (4): 305–60. https:/​/​doi.org/​10.1016/​0304-405X(76)90026-X.
Google Scholar
Laffont, J.-J., and J. Tirole. 1993. A Theory of Incentives in Procurement and Regulation. MIT Press.
Google Scholar
Lehtonen, M., and A. Bhave. 2017. “Learning from Procurement Failures in Complex Infrastructure Projects.” Infrastructure Complexity 4 (1): 1–19. https:/​/​doi.org/​10.1186/​s40551-017-0022-2.
Google Scholar
Massachusetts Bay Transportation Authority. 2014. MBTA Orange and Red Line Vehicle Procurement Contract Award. MBTA Office of the General Manager.
Mizutani, F., and S. Uranishi. 2013. “Does Vertical Separation Reduce Cost? An Empirical Analysis of the Rail Industry in European and East Asian OECD Countries.” Journal of Regulatory Economics 43 (1): 31–61. https:/​/​doi.org/​10.1007/​s11149-012-9193-4.
Google Scholar
Nash, C., and A. Smith. 2021. “Rail Franchising: Learning from the British Experience.” Research in Transportation Economics 83: 100925. https:/​/​doi.org/​10.1016/​j.retrec.2020.100925.
Google Scholar
National Defense Authorization Act for Fiscal Year 2020, Pub. L. Nos. 116–92 (2019).
National Institute of Standards and Technology. 2022. Digital Quality Assurance Frameworks for Complex Manufacturing: A Technical Review. NIST Special Publication 800-222. https:/​/​doi.org/​10.6028/​NIST.SP.800-222.
Polanyi, M. 1966. The Tacit Dimension. Doubleday.
Google Scholar
Procurement Executive Advisory Council. 2021. Vendor Risk Assessment in Complex Capital Procurement. National Transit Procurement Forum Working Paper.
Saltzman, J., and M. Finucane. 2022. “MBTA’s Troubled CRRC Rail Cars: A Timeline of Defects and Delays.” The Boston Globe.
Transportation Research Board. 2016. Improving Transit Agencies’ Technical Capacity for Rolling Stock Procurement. TCRP Report 184. National Academies of Sciences, Engineering, and Medicine. https:/​/​doi.org/​10.17226/​23601.
U.S. Department of Transportation, Office of Inspector General. 2019. FTA Has an Opportunity to Further Promote Lessons Learned to Enhance the Protection of Rolling Stock at Transit Agencies. OIG Rep. No. ZA2019048. https:/​/​www.oig.dot.gov/​library-item/​36700.
U.S. Department of Transportation, Office of Inspector General. 2024. FTA’s Oversight of SEPTA’s Compliance with Buy America Rolling Stock Requirements Faced Several Challenges. OIG Rep. No. ZA2024033. https:/​/​www.oig.dot.gov/​library-item/​37858.
U.S. Government Accountability Office. 2010. Transit Rail: Characteristics of the U.S. Transit Rail Car Market. GAO-10-730. https:/​/​www.gao.gov/​products/​gao-10-730.
U.S. Government Accountability Office. 2019. Rail Transit: Federal Transit Administration Could Improve Information to Better Oversee Capital Programs. GAO-19-562. https:/​/​www.gao.gov/​products/​gao-19-562.
U.S. Government Accountability Office. 2020. Public Transit: FTA Could Take Additional Steps to Help Transit Agencies Address Procurement Challenges. GAO-20-663. Government Accountability Office.
Uyarra, E., and K. Flanagan. 2010. “Understanding the Innovation Impacts of Public Procurement.” European Planning Studies 18 (1): 123–43. https:/​/​doi.org/​10.1080/​09654310903343567.